FİLYOS PORT

FILYOS PORT UNDERWATER FILLING PROJECT

 

Location                : Zonguldak, Turkey

Period                   : 07.2017 – 12.2017

Employer                : TURKISH PETROLEUM OFF-SHORE TECHNOLOGY CENTER INC.

Contractor              : KOLİN & BAYBURT GROUP JOINT VENTURE

Subcontractor          : LCM ROTA CONSTRUCTION AND MARITIME TRADE LTD. CO.

  • Underwater filling was carried out using a total of 2,107,540 tons of material for the construction of the port breakwater.
  • The filling works were completed up to 13.00 meters below sea level, with a placement tolerance of ±0.50 m.