SAKARYA GAS FIELD DEVELOPMENT PROJECT PHASE 2
Location : Zonguldak, Turkey
Period : 07.2024 - 09.2024
Employer : TP-OTC (TURKISH PETROLEUM OFF-SHORE TECHNOLOGY CENTER)
Main Contractor : SAIPEM S.p.A.
Contractor : ARAS DENİZ İNŞAAT A.Ş. (ARAS MARINE CONSTRUCTION INC.)
Subcontractor : LCM ROTA CONSTRUCTION AND MARITIME TRADE LTD. CO.
- Within the scope of the project, 50,000 m³ of channel dredging work was carried out.
- Channel dredging was carried out from -6.00 meters to -19.20 meters in the sections of kilometers KP333-KP600 and KP900-KP1260 of the natural gas pipeline.
- Slope arrangement and cuttings were made.
- The material from the channel dredging was discharged to the designated coordinates for reuse.